The City of Santa Barbara will begin a series of paving projects to repair local streets and enhance our transportation infrastructure. Paving work will begin this week and continue through the end of March, weather dependent. Additional location-specific notifications will also be provided to businesses and residents.

Below is a chart with the detailed paving schedule. Under Project & Contractor where it says the Area (letter), please refer to the map PDF linked below. Under Location where it says shown in (color), please refer to the map as well.  

Project & ContractorDatesLocation
State Street
(Granite Construction)
(Area A)
Feb. 24 – 28Connecting streets to State Street- shown in orange
March 3-11Las Positas Road to East Constance Avenue- shown in red
March 12-13 (night work)Intersection of State Street & Las Positas Road- shown in brown

Garden & Olive Streets
(Lash Construction)
(Area B)
Feb. 27 – March 6Garden Street (E. Los Olivos to E. Islay Streets) - shown in purple
Mid-March (night work, TBD)Olive Street (Anapamu to Sola Streets) - shown in purple

Haley & Anacapa Streets
(Lash Construction)
(Area C)
Feb. 27 – March 6Haley Street (Bath to Garden Streets) - shown in light blue
Anacapa Street (Haley to Cota Streets) - shown in light blue
Mid-March (night work, TBD)Haley Street (Garden to Salsipuedes Streets) - shown in dark blue
Anacapa Street (Cota to Haley Streets)
Intersection of Anacapa and Gutierrez Streets

Cabrillo/Los Patos Roundabout
(Granite Construction)
(Area D)
March 17 – 20 
(night work)
Cabrillo Roundabout

San Andres & Canon Perdido Streets
(Granite Construction)
(Area E)
March 24 – 25San Andres Street (Carrillo Street to Canon Perdido Street) - shown in green
Canon Perdido Street (San Andres Street to Marilla Avenue) - shown in green

Please expect temporary road closures, detours, and traffic delays throughout town as multiple projects occur concurrently. During paving operations, streets will be closed between 7:00 a.m. – 7:00 p.m. Streets that will be paved overnight will be closed from 7:00 p.m. to 7:00 a.m. Hours are subject to change due to weather or any complications that might occur during the paving process. During this time, there will be no access in or out of driveways. Impacted areas will be posted with no parking signs. Please park outside of the posted areas during this process.

These Projects are primarily funded through local Measure C tax dollars.

The City appreciates the public’s patience and cooperation as we work to improve our streets.

For more information, visit SantaBarbaraCA.gov/Streets or contact Adam Ziets, Project Engineer II, at (805) 897-1981 or AZiets@SantaBarbaraCA.gov.