Paving Alameda Padre Serra and Eucalyptus Hill Road Starting July 28
Beginning Tuesday, July 28, through Tuesday, August 4, the City of Santa Barbara Streets Operations Division will be paving Alameda Padre Serra and Eucalyptus Hill Road. See the map and below for a detailed schedule.
Paving Schedule:
Tuesday, July 28 (green on map):
Salinas Street - APS Roundabout
Wednesday, July 29 (purple on map):
300 – 600 blocks of APS (Northbound Lane)
Thursday, July 30 (orange on map):
300 – 600 blocks of APS (Southbound Lane)
Monday, August 3 (red on map):
00 - 200 blocks of APS (Northbound Lane)
1800 block of Eucalyptus Hill Rd.
Tuesday, August 4 (blue on map):
00 - 200 blocks of APS (Northbound Lane)
1800 block of Eucalyptus Hill Rd.
During this project, you may experience temporary delays and parking restrictions. There will be no access in or out of your driveways between the hours of 7:00 a.m. – 5:00 p.m. while paving is occurring. Hours are subject to change due to weather or any complications that might occur during the paving process. Areas will be posted with NO PARKING signs. Please park outside of the posted areas during this process.
QUESTIONS? Please call Mike Krashefski, Streets Operations & Maintenance Superintendent at (805) 564-5454 or email MKrashefski@SantaBarbaraCA.gov.