The City of Santa Barbara Street Operations Production Paving Crew will be paving roads in your neighborhood starting end of June 2024 and is anticipated to be completed early August 2024.

WHAT TO EXPECT: The project will be broken up into five phases: repairing failed sections of the road, lowering utilities, milling the road, paving the road, and raising the utilities up to grade. During these phases, the street will be closed to through traffic between the hours of 7:00 a.m. – 5:00 p.m. 

You will have access in and out of your driveways with delays during all the phases except PAVING days. On PAVING days there will be no access in and out of your driveways between the hours of 7:00 a.m. – 5:00 p.m. Areas will be posted with NO PARKING signs. Please park outside of the posted areas during this process. A more detailed paving schedule notice will be distributed as paving days get closer.

QUESTIONS? Contact Mike Krashefski, Streets Operations & Maintenance Superintendent, at MKrashefski@SantaBarbaraCA.gov or call Streets Operations at (805) 564-5454.