Title

Desal Link Pipeline Project Update (Revised)

Authored on
Body

More than 1,650 feet of Desal Link pipeline has been installed on the first three blocks of Garden Street between Mission and Valerio Streets. Initially, crews were encountering delays due to large boulders and a significant amount of historic trolley tracks under the street. Having dealt with those issues, construction is moving down Garden Street toward Alameda Park. Local roads will remain accessible to residents but will be closed in 3 block sections during active construction.