Project Timeline (Pending Funding)

1
June 2018

Community outreach and plan development.

2
September 2021

Project approval at Planning Commission.

3
January 2022 - June 2023

Project design finalized.

4
July 2023 - December 2023

Construction documents finalized, building permits obtained.

5
January 2024 - March 2024

Project bidding and construction contract awarded.

6
March 2024 - May 2024

Murals removed, stored safely before relocation in the park.

7
May 2024 - June 2025

Project construction and reinstallation of murals.

8
June 2025

Ortega Park reopens!