11 Primary Treatment
The main objective of the Primary Treatment System is to physically separate waste solids from the liquid stream through a clarification…
11 Primary Treatment
There are 5 Primary Clarifiers equipped with sludge and scum collectors. The main objective of the Primary Treatment System is to…
11 Primary Treatment
Primary Sludge is transferred from the Primary Clarifiers to the Gravity Thickener primarily using two Chopper (centrifugal) pumps. A third…
11 Primary Treatment
Primary Scum is collected in a wet well before being transferred from the Primary Clarifiers to the Dissolved Air Flotation Thickener with…

SOP Content Pages

Operators routinely check for normal operation of the Primary Clarifier equipment during daily rounds, at least 2 times per 24 hour period…
Operators routinely check for normal operation of the Primary Clarifier equipment during daily rounds, at least 2 times per 24 hour period…
Shutting down a clarifier involves taking the scum collector and sludge collection units offline.  Also, the sludge transfer piping…
Shutting down a clarifier involves taking the scum collector and sludge collection units offline.  Also, the sludge transfer piping…
Starting up a clarifier involves putting the scum collector and sludge collection units into service. Also, open the valves on the…
The Primary Sludge Pumps serve two main purposes:Transfer of sludge from the Primary Clarifiers to the Gravity Thickener.Drain sludge from…
The Primary Sludge Pumps serve two main purposes:Transfer of sludge from the Primary Clarifiers to the Gravity Thickener.Drain sludge from…
The Primary Sludge Pumps serve two main purposes:Transfer of sludge from the Primary Clarifiers to the Gravity Thickener.Drain sludge from…
Starting up a clarifier involves putting the scum collector and sludge collection units into service. Also, open the valves on the…