The Montecito Branch book drop will be closed May 3rd - 6th due to parking lot repaving

18477

Help shape the future of Santa Barbara's Waterfront! Respond to our survey at SantaBarbaraCA.gov/WaterfrontSurvey.
¡Ayúdanos a dar forma al futuro de la zona costera de Santa Bárbara! Responde a nuestra encuesta en SantaBarbaraCA.gov/WaterfrontSurvey.

18380

All SBPL locations will be closed on Tuesday, May 5, 2026 (5/5/26) for a staff training.

Eastside and Montecito Libraries will close at 2pm on Wednesday, May 6, 2026 (5/6/26) for a staff training.

18362
Title

O & M Manual

Sections
13 PFE Disinfect & Dechlor
Disinfection, Dechlorination, Effluent Monitoring and Effluent Discharge
13 PFE Disinfect & Dechlor
The Chlorine Contact Chamber provides disinfection and dechlorination prior to Ocean Discharge of Secondary Effluent. It is equipped with a…
13 PFE Disinfect & Dechlor
The Sodium Bisfulfite System was abandoned and replaced in 2015 with the Tertiary Filter Upgrade Project. Additional pumps for CIP…
13 PFE Disinfect & Dechlor
Secondary Effluent is discharged to the ocean via a 1.5 mile long ocean outfall. Diffusers are spread along the last quarter mile of the…
13 PFE Disinfect & Dechlor
When the desalination plant was reactivated, Brine discharge was resumed and additional analytical and sampling equipment was added to…

SOP Content Pages

The chlorine residual anaylzers are used to control the amount of sodium bisulfite required to dechlorinate effluent.  The application…
Sodium bisulfite is injected to the chlorine contact chamber (CCC) effluent prior to discharge for dechlorination purposes. …
Addressing the loss of disinfection is generally a series of troubleshooting activities and corrective actions. Typical causes of a…
Total results: 5 1

Plant Schematic

El Estero Schematic Drawing