Title

15 DAFT Shutdown SOP

Two SOPs are provided for DAFT Shutdown. 

  • Short term shutdown shuts off all feed to the DAFT. 
  • Long term shutdown bypasses flows away from the DAFT to an available digester or an empty aeration basin. Long term bypassing to a digester, however, could overload the digesters.
SOP Identification Number
SOP Identification Number:
1502_Daft Shutdown
Purpose and scope
Purpose and scope:

Reasons to take the Dissolved Air Flotation Thickener (DAFT) {tag no. 1502STRU0001} out of service may include routine maintenance, tank cleaning, repairs to piping, or some kind of work that is required on an upstream or downstream process.

Three systems feed into the DAFT:

·         Waste Activated Sludge (WAS)

·         Primary Scum

·         Secondary Scum.

Definitions
Definitions:
  • DAFT:  Dissolved Air Flotation Thickener
Health & Safety Warnings
Health & Safety Warnings:

Watch for open tanks and high elevations.  If working on or near equipment, watch for moving parts.

Cautions
Cautions:

Long term DAFT bypassing to a digester could overload the digesters.

Potential Interferences
Potential Interferences:
  • If the DAFT must be bypassed for a long period of time, and empty aeration basin or digester must be available and have capacity for bypassed sludge flow.
Personnel Qualifications
Personnel Qualifications:


Operator I, knowledge of thickening process and equipment controls

Quality Control/Quality Assurance Activities for the Procedure
Quality Control/Quality Assurance Activities for the Procedure:
  • Record activity to log book.
  • Monitor A/S ratio and adjust air flow if necessary to maintain optimal A/S ratio.
  • Monitor thickeness of floating sludge.  Adjust rake speed if necessary to maintain optimal depth
Procedure
Procedure:

Short Term DAFT Shutdown:  If the DAFT is to be taken offline for a relatively short period of time, the following SOP may be performed.

1.     Turn off Dissolution System.

a.     Reduce the pressure from the back pressure valve {tag no. 1502VLV5687C}.  The valve is located at the exterior base of the DAFT structure near the bottom of the stairs. This reduces the strain on the Dissolution System Pump Motors {tag nos. 1502PMP5100, 1502PMP5100A, 1502PMP5200, 1502PMP5200A & 1502MTR5100A, 1502MTR5200A} and will make start up much easier when the system is put back online. If the DAFT feeds (WAS, Primary Scum and Secondary Scum) are turned off before the Dissolution System is shut down, the Dissolution System Pumps will air-lock and run dry.

2.     Isolate Feeds to DAFT

a.     Turn off WAS flow to the DAFT.

                      i.        Turn off the WAS pumps {tag nos. 1205PMP2100 & 1205PMP2200}.

                     ii.        Lock out/tag out the pump.

                    iii.        Close the WAS Suction Isolation Valves {tag nos. 1205VLV2100 & 1205VLV2200}.

                    iv.        Close the WAS Discharge Isolation Valves {tag nos. 1205VLV2100A & 1205VLV2200A}.

b.     Turn off Primary Scum flows to the DAFT.  Primary Scum pumping can be shut down for up to 3-4 days.

                      i.        Turn off the Primary Scum Pumps {tag nos. 1103PMP1100 & 1103PMP1200}.

                     ii.        Lock out/tag out the pump.

                    iii.        Close the Primary Scum Suction Valves {tag nos. 1103VLV1100 & 1103VLV1200}..

                    iv.        Close the Primary Scum Discharge Valves {tag nos. 1103VLV1100A & 1013VLV1200A}.

                     v.        Turn off the Primary Scum Skimmers {tag no. 1101COL1171 & 1101COL1172}.

c.     Turn off Secondary Scum Pumping to the DAFT.  Secondary Scum pumping can be shut down for up to 3-4 days.

                      i.        Turn off the Secondary Scum Pumps {tag no. 1207PMP2100 & 1207PMP2200}.

                     ii.        Lock out/tag out the pump.

                    iii.        Close the Secondary Scum Suction Valves {tag nos. 1207VLV2679 & 1207VLV2679A}.

                    iv.        Close the Secondary Scum Discharge Valves {tag nos. 1207VLOV2100A & 1207VLV2200A}.

                     v.        Turn off the Secondary Scum Skimmers {tag nos. 1203COL2171 & 1203COL2172}. The Sludge Collector {tag no. 1203COL2161 & 1203COL2261} can remain in operation.

d.     Turn off the Polymer Feed to the DAFT.

                      i.        Close the DAFT Polymer Feed Suction Valve {tag no. 1502VLV5671}.

3.     Turn off TSPS Pump. The pump is normally controlled by levels in the wet well.

a.     Turn off TSPS Pump #1 {tag no. 1503PMP5100} at the HOA Switch {tag no. 1503HS5100D}.

b.     Lock Out/Tag Out the pump.

4.     Turn off the DAFT Rake.

a.     Turn off DAFT Rake {tag no. 1503RAK/MTR5300} at the HOA Switch {tag no. 1503HS5300}.

b.     Lock Out/Tag Out the Rake.

5.     Turn off the DAFT Automatic Sampler.

a.     Turn off the DAFT Automatic Sampler {tag no. 1502SAMP3151}, which is located at the building exterior.

 

Long Term DAFT Shutdown:  If the DAFT is to be shut down for more than a couple of days, the following SOP should be performed.  Sludge can be stored in an aeration basin for up to 3 – 4 days.

1.     Turn off Dissolution System.

a.     Reduce the pressure from the back pressure valve {tag no. 1502VLV5687C}.  The valve is located at the exterior base of the DAFT structure near the bottom of the stairs. This reduces the strain on the Dissolution System Pump Motors {tag nos. 1502PMP5100, 1502PMP5100A, 1502PMP5200, 1502PMP5200A & 1502MTR5100A, 1502MTR5200A} and will make start up much easier when the system is put back online. If the DAFT feeds (WAS, Primary Scum and Secondary Scum) are turned off before the Dissolution System is shut down, the Dissolution System Pumps will air-lock and run dry.

2.     Bypass flows to an available aeration basin.

a.     Locate the valve(s) {tag nos. 1201VLV2182, 1201VLV2184, 1201VLV2186, 1201VLV2188, 1201VLV2190} in Gallery 3 that are associated with the aeration basin used for bypass.  Adjust the valve(s) so that flows into the aeration basin are near the SRT target flow.

b.     Monitor the flow and adjust the valve(s) as necessary.

c.     When the sludge level in the aeration basin reaches the top of the air discs, open the Diffuser Air Isolation valve(s) {tag nos. 1201VLV2233, 1201VLV2235, 1201VLV2237, 1201VLV2239, 1201VLV2241} for that aeration basin.   Adding air to the sludge will help maintain a viable biomass and keep the tank from going septic.

3.     Turn off TSPS Pump. The pump is normally controlled by levels in the wet well.

a.     Turn off TSPS Pump #1 {tag no. 1503PMP5100} at the HOA Switch {tag no. 1503HS5100D}.

b.     Lock Out/Tag Out the pump.

4.     Turn off the DAFT Rake.

a.     Turn off DAFT Rake {tag no. 1503RAK/MTR5300} at the HOA Switch {tag no. 1503HS5300}.

b.     Lock Out/Tag Out the Rake.

5.     Turn off the DAFT Automatic Sampler.

a.     Turn off the DAFT Automatic Sampler {tag no. 1502SAMP3151}, which is located at the building exterior.

6.     Pump stored sludge back into the DAFT.  Perform Step 3 when the DAFT is to be put back into service.

a.     Locate the Secondary Scum Drainage valves.  Adjust the valve(s) to pump the stored sludge into the DAFT at a controlled rate.

 

Drain DAFT Tank:  Perform the following SOP if the DAFT tank needs to be drained, while it is offline.

1.     Drain DAFT Tank.

a.     Locate the isolation valve {tag no. 1502VLV5684} for the DAFT drain line, which is located at the curb between two bollards.

b.     Connect the portable pump and hose to the connection.  Direct the discharge to the nearest sanitary sewer manhole (located nearby in the roadway).

c.     Turn on the pump.  Monitor the volume in the DAFT tank until it is drained.

 

Record Data to Operator’s Log Book:

1.     Record DAFT Activities to the log book with other entries for the day.  Include the following in the entry:

·         Operator(s) that performed the DAFT SOP.

·         Note condition of equipment, piping, valves, etc.

·         Note any unusual conditions with flows, levels, odors or other process issues.

·         Note any damage, wear, or required maintenance on equipment.

Data & Records Management, Calculations, Forms, Reports
Data & Records Management, Calculations, Forms, Reports:
  • Update log book.
  • Update maintenance records (if applicable).
  • Report any maintenance or attention that is required.
Equipment
Equipment:

EQUIPMENT NAME

TAG NUMBER

DAFT Local Control Panel

1502BKT5300

DAFT Drive Unit Breaker Switch

1502BKR5300

DAFT Panel HOA

1502HS5300

DAFT Panel Hand Switch

1502HS5300B

DAFT Panel Indicator Light

1502YL5300

DAFT Drive Unit

1501VSD5300

DAFT Drive Unit Motor

1501MTR5300

Back Pressure Valve

1505VLV5687C

Pressure Gauge

1505PI5687

Suction Valve

1502VLV5100

Suction Valve

1502VLV5200

Discharge Valve

1502VLV5100F

Discharge Valve

1502VLV5200G

Discharge Valve Pump 1 & 2

1502VLV5687A

Dissolution System Recycle Pump Panel

1502BKT5100

Dissolution System Recycle Pump Panel Breaker Switch

1502BKR5100

Dissolution System Recycle Pump Panel Hand Switch

1502HS5100

Dissolution System Recycle Pump 1

1502PMP5100

Dissolution System Recycle Pump 2

1502PMP5200

Dissolution System Flow Meter

1502FE/FIT5676

Dissolution System Air Valve

1502FCV5673

Dissolution System Air Valve

1502FCV5674

Dissolution System Tank

1502TNK5691